CENIC Projects Schedule FY24/25-DRAFT
The following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations or replacement of end-of-life (EOL) routers. This project plan is not static and may change depending on new requests, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule below reflects the month that the college district evaluation meeting occurred and approved the network topology map, or the month of finalization of the plan and order of the circuit, or the scheduled month for router replacements. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.
Circuits Orders & Router Replacements Planned
Remaining 2023-2024 Circuit Evaluations, Not Completed
Coast CCD (moved from 23/24; no response from college)
Coastline Community College 10GB upgrade
Kern CCD - New Request
Bakersfield Arvin Campus 2x 1GB
Bakersfield Southwest Center 2x 1GB
Los Rios CCD (originally met in and moved from 23/24; majority of circuits ordered September/October 2024)
Elk Grove Center 1GB (No Bid on diverse secondary)
Sequoias CCD (originally requested in and moved from 23/24 as CENIC needed to research sites before ordering; plan finalized XX and circuits ordered XX)
Hanford Center 1GB
Tulare Center 1GB
Solano County CCD (evaluated 23/24, college requested 10GB circuits, still working with VAST on options; moved to 24/25)
Vacaville Center 1GB -->10GB Requested
Vallejo Center 2x 1G -->10GB Requested
Districts with Priority EOL Router Replacements
Peralta CCD - 6 ASR1001-X and 2 ASR9001
CCCCO Data Center - ASR1001-X; replacement in progress with 10GB circuit upgrade
Chaffey CCD - 2 ASR1001-X and 3 ASR9001
Contra Costa CCD - ASR1001-X; replacement in progress with 10GB circuit upgrade
Foothill CCD - ASR1001-X and 4 ASR9001
Glendale CCD - 3 ASR1001-X and 4 ASR9001
Los Rios CCD - 4 ASR1001-X; to be replaced as center site circuits are installed - not ordered yet
Mira Costa CCD - ASR1001-X and 2 ASR9001
Mt. San Jacinto CCD - ASR1001-X; replacement in progress with 1GB circuit install at Meniffee, need to decommission EOL router
Ohlone CCD - ASR1001-X and 3 ASR9001
Palomar CCD - 3 ASR1001X; can be replaced with the circuit move for North Education Center - not ordered yet
San Bernardino CCD - ASR1001-X; replacement in progress with 1GB diverse circuit install and 4 ASR9001 can be replaced while working on new center, diverse circuit for DO, and e-line - not ordered yet
San Jose-Evergreen CCD - ASR1001-X; replacement in progress with 1GB circuit install at Meniffee, need to decommission EOL router
Santa Barbara CCD - ASR1001X and ASR9001; replacement in progress with 10GB City College diverse circuit
Shasta CCD - 6 ASR1001-X; replacement in progress with Trinity-Burney Center, can include the others in the process
South Orange County CCD - 2 ASR1001-X and 2 ASR9001; replacements in progress with 1GB circuit install at Meniffee, need to decommission EOL routers
Southwestern CCD - 8 ASR1001-X
Yuba CCD - 3 ASR1001-X; circuits in progress, not the correct sites but Ken will reach out
Monthly Circuit Evaluation / Router Replacement Schedules & Updates
July 2024
Allan Hancock CCD - New Request (requested and approved July 2024; plan finalized and circuits ordered in August)
Lompoc Valley Center 2x 10GB upgrade
Butte-Glenn Community College District (originally met in and moved from 23/24 due to no diversity for secondary circuits; plan finalized July 2024; circuits ordered XX)
Chico Center 2x 1GB
Cosmetology Center 2x 1GB
Glenn County Center 2x 1GB
Skyway Center 2x 1GB
Gavilan CCD (originally met in and moved from 23/24 as site not ready; plan finalized July 2024. Circuits ordered September 2024 with a December ETA)
San Benito Campus 2x 1GB
Hartnell CCD (moved from 23/24 due to no response from college; plan finalized July 2024. Circuits ordered September 2024)
Castroville Campus 1GB secondary
King City Center 1GB secondary
Soledad Campus 1GB secondary
August 2024
San Francisco CCD (met and finalized plan 23/24, circuits ordered August 2024)
Mission CC Center 1GB
Chinatown Center 1GB (New Request)
State Center CCD (evaluated 22/23, reevaluated 23/24, contracts not completed. Plan finalized May 2024; contracts completed and circuits ordered August 2024)
State Center CCD 2x 10GB
Clovis CC 100GB primary & 10GB secondary
Reedley College 100GB primary & 10GB secondary
Madera College 10GB
Career & Technology Center 1GB
Clovis Herndon Campus 1GB
Oakhurst Center 100Mbps
River Park Place Campus 1GB
Fulton Mall District Office 10GB
West Fresno Center 100GB
First Responders Center 10GB
Siskiyous CCD (reevaluated May 2024, researched options; ordered August 30th)
Yreka Campus 1GB (Rebid)
EOL Router Replacement Updates
08/08/2024: Received list of EOL routers
08/23/2024: Developed strategy to collect necessary information and schedule router replacements
08/27/2024: Developed Google form to collect info CENIC engineering will need and start scheduling router replacements
September 2024
Los Rios CCD (originally met in and moved from 23/24; plan is not completed yet)
Davis Center 2x 1 GB
El Dorado Center 2x 1GB
Elk Grove Center 1GB (No Bid on secondary)
Ethan Way Center 2x 1GB - added
Facilities Management 2x 1GB - added
Mather Center 2x 1GB
Mather Center2 1GB - added
McClellan Aero 2x 1GB
McClellan Center 2x 1GB
McClellan Hanger/Tool Center 1GB - added
McClellan Park 2x 1GB
Natomas Center 2x 1GB - added
Rancho Cordova Ed Center 2x 1GB
Twin Rivers Center 1GB - canceled
West Sacramento Center 2x 1GB
Marin CCD - New Request
College of Marin-Bolinas Biology Lab
San Francisco CCD - New Request
City College of San Francisco 10GB diverse
EOL Router Replacement Updates
09/03/2024: Met with CCCTC Marketing to discuss and plan use of a Constant Contact campaign to notify colleges of need to replace routers and expectation of receipt of an email with a survey/scheduling form
09/04/2024: Met with CENIC to finalize list of districts that the Constant Contact messages will be sent
09/04/2024: Received outline of the router replacement campaign and draft of the first message from CCCTC Marketing
09/06/2024: Reviewed and provided feedback to CCCTC Marketing on the draft Constant Contact message
09/09/2024: Provided CCCTC Marketing with contact list for messages
09/11/2024: 1st of 2 Router Replacement Constant Contact messages was sent out to targeted list of recipients
09/25/2024: 2nd of 2 Router Replacement Constant Contact messages was sent out to targeted list of recipients
October 2024
EOL Router Replacement Updates
10/10/2024: Received feedback and edits from CENIC on EOL Router Replacement Scheduling survey
10/15/2024: Sent all direct notification emails to college districts who have the older EOL router model that needs to be replaced in 2024-25
November 2024
Shasta-Tehama-Trinity Joint CCD
Trinity Center 1GB (Rebid for Diversity?)
December 2024
January 2025
February 2025
March 2025
Foothill-De Anza CCD
Foothill College 10GB (Rebid for Diversity?)
April 2025
May 2025
June 2025
Los Angeles CCD
East LA College 100GB upgrade (college-paid)
LA Valley College 100GB upgrade (college-paid)
Peralta CCD (future - check in Summer 2025, per district; building completion estimated 2026)
Berkeley City College 2x 1GB
Redwoods CCD (originally met in and moved from 22/23 and researched options in 23/24; hold for MM and LM Fiber Projects)
City of Hoopa 2x 1GB
Quarterly Progress on Circuit Installations
FY24/25 Circuits | Circuits Reprioritized and/or Added to Original Plan1 | Planned Prioritized Circuits2 | Circuits Implemented, In Production to Date | Planned Circuits Ordered, in Process of Implementation3 | Planned Circuits Pending Review and/or Order | Planned Circuits Canceled4 | Planned Circuits Rescheduled for Future Year5 |
---|---|---|---|---|---|---|---|
Quarter 1: July - September 2024 | 0 | 29 | 0 | 0 | 29 | 0 | 0 |
Quarter 2: October - December 2024 |
|
|
|
|
|
|
|
Quarter 3: January - March 2025 |
|
|
|
|
|
|
|
Quarter 4: April - June 2025 |
|
|
|
|
|
|
|
1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.
2 Includes all reprioritized and new circuit requests as noted above.
3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.
4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.
5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.
For Questions or More Information Contact:
CCC Technology Center:
Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org
CENIC:
Ken Roberts, Project Manager CCC Segment kroberts@cenic.org
To Report Network Routing or Technical Issues:
CENIC NOC (available 24/7):
Email: noc@cenic.org
Phone: 714-220-3494