Circuits Evaluation Schedule FY24/25

The following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations. This project plan is not static and may change depending on how the circuit priorities change as impacted by construction, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule reflects the month that the college district was or will be contacted for a circuit upgrade evaluation meeting and review of the district’s network topology map. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.


July 2024

  • Chabot CCD

    • Chabot College (Move Circuits MPOE for CCC-1489 & CCC-1491)

August 2024

  • Foothill-De Anza CCD

    • Los Altos Hills Center (Rebid for Diversity, see notes Jan 2024)

September 2024

October 2024

 

November 2024

December 2024

  • Shasta-Tehama-Trinity Joint CCD

    • Trinity Center 1GB diverse (Rebid for Diversity, see notes Jan 2024)

January 2025

 

February 2025

 

March 2025

April 2025

May 2025

June 2025

  • Desert CCD

    • Roadrunner Motors Site 2x 1GB


Quarterly Progress on Circuit Installations

FY22/23 Circuits

Circuits Reprioritized and/or Added to Original Plan1

Planned Prioritized Circuits2

Circuits Implemented, In Production to Date

Planned Circuits Ordered, in Process of Implementation3

Planned Circuits Pending Review and/or Order

Planned Circuits Canceled4

Planned Circuits Rescheduled for Future Year5

FY22/23 Circuits

Circuits Reprioritized and/or Added to Original Plan1

Planned Prioritized Circuits2

Circuits Implemented, In Production to Date

Planned Circuits Ordered, in Process of Implementation3

Planned Circuits Pending Review and/or Order

Planned Circuits Canceled4

Planned Circuits Rescheduled for Future Year5

Quarter 1: July - September 2022

 

 

 

 

 

 

 

Quarter 2: October - December 2022

 

 

 

 

 

 

 

Quarter 3: January - March 2023

 

 

 

 

 

 

 

Quarter 4: April - June 2023

 

 

 

 

 

 

 

1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.

2 Includes all reprioritized and new circuit requests as noted above.

3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.

4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.

5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.


For Questions or More Information Contact:

CCC Technology Center:

Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org

 

CENIC:

Ken Roberts, Project Manager CCC Segment kroberts@cenic.org

To Report Network Routing or Technical Issues:

CENIC NOC (available 24/7):

Email: noc@cenic.org

Phone: 714-220-3494