Circuits Evaluation Schedule FY22/23
The following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations. This project plan is not static and may change depending on how the circuit priorities change as impacted by construction, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule reflects the month that the college district was or will be contacted for a circuit upgrade evaluation meeting and review of the district’s network topology map. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.
*Note, all circuit evaluations were reprioritized to frontload as many as possible into July-December 2022 timeframe as the routers ordered for FY22/23 arrived 6 months sooner than originally estimated.
July 2022
| August 2022
| September 2022
|
October 2023
| November 2023
| December 2023
|
January 2023
| February 2023
| March 2023
|
April 2024
| May 2024
| June 2024
|
Quarterly Progress on Circuit Installations
FY22/23 Circuits | Circuits Reprioritized and/or Added to Original Plan1 | Planned Prioritized Circuits2 | Circuits Implemented, In Production to Date | Planned Circuits Ordered, in Process of Implementation3 | Planned Circuits Pending Review and/or Order | Planned Circuits Canceled4 | Planned Circuits Rescheduled for Future Year5 |
---|---|---|---|---|---|---|---|
Quarter 1: July - September 2022 | 12 | 55 | 0 | 17 | 37 | 1 | 0 |
Quarter 2: October - December 2022 | 5 | 59 | 1 | 38 | 20 | 1 | 5 |
Quarter 3: January - March 2023 | 3 | 55 | 3 | 38 | 13 | 0 | 0 |
Quarter 4: April - June 2023 | 17 | 72 | 7 | 54 | 8 | 2 | 4 |
1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.
2 Includes all reprioritized and new circuit requests as noted above.
3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.
4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.
5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.
For Questions or More Information Contact:
CCC Technology Center:
Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org