The following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations or replacement of end-of-life (EOL) routers. This project plan is not static and may change depending on new requests, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule reflects the month that the college district was contacted for a circuit upgrade evaluation meeting and review of the district’s network topology map or the month of finalization of the plan and order of the circuit or shipment of the replacement routers. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.


July 2024

  • Butte-Glenn Community College District (originally met in and moved from 23/24 due to no diversity for secondary circuits)

    • Chico Center 2x 1GB

    • Cosmetology Center 2x 1GB

    • Glenn County Center 2x 1GB

    • Skyway Center 2x 1GB

  • Gavilan CCD (originally met in and moved from 23/24 as site not ready)

    • San Benito Campus 2x 1GB

  • Hartnell CCD (moved from 23/24; no response from college)

    • Castroville Campus 1GB secondary

    • King City Center 1GB secondary

    • Soledad Campus 1GB secondary

August 2024

September 2024

Evaluations Not Completed

  • Coast CCD (moved from 23/24; no response from college)

    • Coastline Community College 10GB upgrade

  • College of the Sequoias (originally requested in and moved from 23/24; CENIC researching sites)

    • Hanford Center 1GB

    • Tulare Center 1GB

  • Los Rios CCD (originally met in and moved from 23/24; plan is not completed yet)

    • Davis Center 1 GB

    • El Dorado Center 1GB

    • Elk Grove Center 1GB

    • Ethan Way Center 1GB - added

    • Mather Center 1GB

    • McClellan Center 2x 1GB

    • McClellan Diesel Auto Center 1GB - added

    • Natomas Center 1GB - added

    • Rancho Cordova Center 1GB

    • Twin Rivers Center 1GB - canceled

    • West Sac Center 1GB

  • Redwoods CCD (originally met in and moved from 22/23 and researched options in 23/24; still trying to finalize plan)

    • City of Hoopa 2x 1GB

  • San Francisco CCD (met and finalized plan in 23/24, did not get circuits ordered; moved to 24/25)

    • Mission CC Center 1GB

  • Siskiyous CCD (reevaluated May 2024, still researching options; moved to 24/25)

    • Yreka Campus 1GB (Rebid)

  • Solano County CCD (evaluated 23/24, still working with VAST; moved to 24/25)

    • Vacaville Center 1GB

    • Vallejo Center 2x 1G

  • State Center CCD (evaluated 22/23, reevaluated 23/24, contracts not completed; moved to 24/25)

    • State Center CCD 2x 10GB

    • Clovis CC 100GB primary & 10GB secondary

    • Reedley College 100GB primary & 10GB secondary

    • Madera College 10GB

    • Career & Technology Center 1GB

    • Clovis Herndon Campus 1GB

    • Oakhurst Center 100Mbps

    • River Park Place Campus 1GB

    • Fulton Mall District Office 10GB

    • West Fresno Center 100GB

    • First Responders Center 10GB

  • Ventura CCD

    • Ventura East 10GB secondary

    • Ventura Fire & Safety Training Center 1GB secondary

November 2023

  • Shasta-Tehama-Trinity Joint CCD

    • Trinity Center 1GB (Rebid for Diversity)

January 2025

February 2025

March 2025

  • Foothill-De Anza CCD

    • Foothill College 10GB (Rebid for Diversity)

April 2025

May 2025

June 2025

  • Los Angeles CCD

    • East LA College 100GB upgrade (college-paid)

    • LA Valley College 100GB upgrade (college-paid)

  • Peralta CCD (future - check in Summer 2025, per district; building completion estimated 2026)

    • Berkeley City College 2x 1GB


Quarterly Progress on Circuit Installations

FY24/25 Circuits

Circuits Reprioritized and/or Added to Original Plan1

Planned Prioritized Circuits2

Circuits Implemented, In Production to Date

Planned Circuits Ordered, in Process of Implementation3

Planned Circuits Pending Review and/or Order

Planned Circuits Canceled4

Planned Circuits Rescheduled for Future Year5

Quarter 1: July - September 2024

0

29

0

0

29

0

0

Quarter 2: October - December 2024

Quarter 3: January - March 2025

Quarter 4: April - June 2025

1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.

2 Includes all reprioritized and new circuit requests as noted above.

3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.

4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.

5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.


For Questions or More Information Contact:

CCC Technology Center:

Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org

CENIC:

Ken Roberts, Project Manager CCC Segment kroberts@cenic.org

To Report Network Routing or Technical Issues:

CENIC NOC (available 24/7):

Email: noc@cenic.org

Phone: 714-220-3494