Systemwide Implementation Timeline

Systemwide Implementation Timeline

Milestone

Month

Milestone

Month

Implementation Phase Kick-off

Late January 2019

Implementation Test Loads

March-April

Implementation Alma/Primo Env. Available

May

Implementation Data Review & Integrations

May-October

Implementation Workshops II (4) x 2 days

September

Provision local SFTP servers for SIS loads

October

Authentication Forms complete

October

3rd Party Integrations complete

October

Alma Certification complete

October-November

Primo Certification complete

October-November

Implementation Go-Lives

December -January

Configuration refinements/review

January-February 2020

Switch to Support/ Project Close

March 2020

Questions? Contact Amy Beadle, Project Lead at abeadle@ccctechcenter.org