Systemwide Implementation Timeline
| Milestone | Month |
|---|---|
| Implementation Phase Kick-off | Late January 2019 |
| Implementation Test Loads | March-April |
| Implementation Alma/Primo Env. Available | May |
| Implementation Data Review & Integrations | May-October |
| Implementation Workshops II (4) x 2 days | September |
| Provision local SFTP servers for SIS loads | October |
| Authentication Forms complete | October |
| 3rd Party Integrations complete | October |
| Alma Certification complete | October-November |
| Primo Certification complete | October-November |
| Implementation Go-Lives | December -January |
| Configuration refinements/review | January-February 2020 |
| Switch to Support/ Project Close | March 2020 |