Legend
c - Complete
- In-Progress
- Not Started
Actively Engaged Colleges
District | DIST MIS | College | MIS | JIRA | DIST IdP | IdP Solution | Start Date | TargetEnd Date | IdP Ready | Proxy Pilot | Proxy Prod | APPLY Pilot | APPLY Prod | CANVAS Pilot | CANVAS Prod | STARFISH Pilot & Prod | Proxy Status | IdP Solution Comment | IdP Domain | SIS | Initiative |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
SOUTHWESTERN | 090 | Southwestern College | 091 | - CIP-671Getting issue details... STATUS | Portal Guard | 8/15/2017 Had kick-off call, SW will be ready for prod in early Sept. | swccd.edu | Colleague | |||||||||||||
SANTA CLARITA | 660 | College of the Canyons | 661 | Shib V3 | 4/12/17 | 6/12/17 | 5/1/17-Proxy Prod/CCC Apply Prod testing successful 7/18/17-Waiting for Canyons to copying Azure AD to local | Unicon- Shib Upgrade Complete | canyons.edu | Colleague | OEI 2 | ||||||||||
CABRILLO | 410 | Cabrillo College | 411 | ADFS (students) Shib V2 | 6/14/17(Matt)Have ADFS metadata, request add to Pilot. 7/18/17-Pending college testing Proxy Pilot | cabrillo.edu | Colleague | OEI 2 | |||||||||||||
HARTNELL | 450 | Hartnell College | 451 | Shib V2 | 7/11/17 | 9/11/17 | 6/6/17(Matt) Bala confirmed desire for Shib v3 upgraded, forwarded to Dave L. to schedule. | 8/28/17: Unicon received remote access–questions pending about IdP's/Configs | hartnell.edu | Colleague | OEI 2 | ||||||||||
SOUTH ORANGE | 890 | Saddleback College | 891 | Yes | Shib v3 | Proxy Production update complete-testing complete | socccd.edu | Homegrown | CAI OEI 2 | ||||||||||||
890 | Irvine Valley College | 892 | Yes | Shib v3 | socccd.edu | Homegrown | CAI | ||||||||||||||
LOS ANGELES | 740 | West Los Angeles College | 749 | Yes | MS ADFS | Proxy Prod update complete--testing in-process 5/4/2017 Spoke with Lawrence, he told me there would need to be internal discussion before working on Canvas PILOT. He told me this a month earlier. Will followup with Albert. 6/1/17(Matt) On hold until August per Albert. | Peoplesoft (In Process) | OEI 2 | |||||||||||||
740 | Los Angeles Pierce College | 744 | MS ADFS | OEI 2 | |||||||||||||||||
740 | East Los Angeles College | 748 | MS ADFS | email.laccd.edu | |||||||||||||||||
740 | Los Angeles City College | 741 | MS ADFS | ||||||||||||||||||
740 | Los Angeles Harbor College | 742 | MS ADFS | ||||||||||||||||||
740 | ITV/The Weekend College | 74A | MS ADFS | ||||||||||||||||||
740 | Los Angeles Mission College | 743 | MS ADFS | ||||||||||||||||||
740 | Los Angeles Trade Technical College | 746 | MS ADFS | ||||||||||||||||||
740 | Los Angeles Valley College | 747 | MS ADFS | ||||||||||||||||||
740 | Los Angeles Southwest College | 745 | MS ADFS | ||||||||||||||||||
MIRA COSTA | 050 | Mira Costa | 051 | Portal Guard | 5/11/2017 Found contact info for Lisa and sent an email to see if we can have a meeting to plan the implementation. 5/24/17 Contacted Mario, was forwarded to Steve Shultz. Steve was out today and will get back to me when he returns. 5/30/17(Matt) Spoke with Steve Shultz, Mira Costa is in the process of migrating to PortalGuard. This should take 6 weeks. Will follow up. 6/29/17-Uploaded metadata to Proxy Pilot and Prod–testing pending | miracosta.edu | Peoplesoft | OEI 2 | |||||||||||||
SANTA MONICA | 780 | Santa Monica City | 781 | Shib V3 | 4/14/17-College's Canvas metadata added to InCommon; Need to work with college to configure Canvas pilot with Proxy | Unicon-Shib Upgrade Complete | smccd.edu | Banner | CAI | ||||||||||||
LOS RIOS | 230 | American River College | 231 | Shib V3 | N/A | N/A | Proxy Production update complete They use different IdPs for Assess (via Proxy) and Apply but plan to consolidate for Admin 2.0. | losrios.edu | Peoplesoft | CAI | |||||||||||
230 | Cosumnes River College | 232 | Shib V3 | N/A | N/A | losrios.edu | Peoplesoft | ||||||||||||||
230 | Sacramento City College | 233 | Shib V3 | N/A | N/A | losrios.edu | Peoplesoft | CAI | |||||||||||||
230 | Folsom Lake College | 234 | Shib V3 | N/A | N/A | losrios.edu | Peoplesoft | ||||||||||||||
CHAFFEY | 920 | Chaffey College | 921 | Shib V3 | Proxy Production update complete–testing complete | Unicon-Shib Upgrade Complete | chaffey.edu | Colleague | CAI | ||||||||||||
CONTRA COSTA | 310 | Contra Costa | 311 | Portal Guard | Proxy Production update complete | 4cd.edu | Colleague | EPI CAI | |||||||||||||
310 | Diablo Valley College | 312 | Portal Guard | CAI | |||||||||||||||||
310 | Los Medanos | 313 | Portal Guard | CAI | |||||||||||||||||
KERN | 520 | Bakersfield | 521 | Yes | Shib V3 - currently using Shib but may pursure ADFS in the future | Proxy Production update complete | Unicon-Shib Upgrade Complete | kccd.edu | Banner | EPI CAI | |||||||||||
520 | Cerro Coso | 522 | Shib V3 | ||||||||||||||||||
520 | Porterville | 523 | Shib V3 | ||||||||||||||||||
SIERRA | 270 | Sierra | 271 | Yes | Upgrading now Shib V3 | Proxy Production update complete–pending college updating production Shib metadata files to include Production Proxy | 7/18: Awaiting updates to Prod IdP | sierra.edu | |||||||||||||
SAN MATEO | 370 | Canada | 371 | Ellucian EIS | 4/21/17-Working issue for Apply Pilot | smccd.edu | Banner | ||||||||||||||
370 | College of San Mateo | 372 | Ellucian EIS | ||||||||||||||||||
370 | Skyline | 373 | Ellucian EIS | ||||||||||||||||||
SANTA BARBARA | 650 | Santa Barbara City College | 651 | Shib v3 | 4/17/17-Tested Proxy Pilot/Prod | College-Completed upgrade as of 3/23/17 | sbcc.edu | Banner | EPI | ||||||||||||
PALOMAR | 060 | Palomar | 061 | PortalGuard | 9/20/17-Received Production Hobsons metadata for upload to Proxy | Unicon-Shib Upgrade Complete | palomar.edu | Peoplesoft | |||||||||||||
GLENDALE | 730 | Glendale Comm College | 731 | Shib v3 | Proxy Production update complete-testing complete | Unicon-Shib Upgrade Complete 2.01.17 | glendale.edu | Peoplesoft | |||||||||||||
CITRUS | 820 | Citrus College | 821 | Shib V3 | 3/1/17 | 5/1/17 | 5/1/17-Proxy Prod anc CCC Apply Prod testing successful | Unicon-Shib Upgrade in-progress | citrus.edu | Peoplesoft | |||||||||||
LONG BEACH | 840 | Long Beach City College | 841 | Shib V2 (Apply) Shib V3 (Cranium Cafe) | 5/1/17-Proxy Pilot and Prod update complete–testing pending 5/10/17 prod test completed. | Long Beach has setup their own Shib V3 instance for Cranium Cafe and will look to migrate their Apply from Shib V2 to V3. | lbcc.edu | Peoplesoft | |||||||||||||
RANCHO SANTIAGO | 870 | Santa Ana College | 871 | Shib V3 Upgrade in-progress | 3/2/17 | 5/2/17 | 6/14/17-Proxy Prod metadata updates complete–testing successfully completed | Unicon-Shib Upgrade In-Process | rsccd.edu | Colleague | |||||||||||
870 | Santiago Canyon College | 873 | rscccd.edu | Colleague | |||||||||||||||||
SAN LUIS OBISPO | 640 | Cuesta College | 641 | Shib V3 | Proxy Production update complete–testing complete | Unicon-Shib Upgrade Complete | cuesta.edu | Banner | |||||||||||||
SEQUOIAS | 560 | College of the Sequoias | 561 | Shib V2 to PG | 5/17/17-Conducted Proxy kick-off mtg 6/14/17-Uploaded Canvas InCommon metadata to Proxy Pilot | 7/11/17-PortalGuard installation underway, will contact Matt once complete. | sequoia.edu | Banner | |||||||||||||
SONOMA | 260 | Santa Rosa | 261 | Shib V3 | Proxy Production update complete | Unicon-Shib Upgrade Complete | santarosa.edu | Santa Rosa | EPI | ||||||||||||
YUBA | 290 | Yuba College | 291 | Yes | PORTAL GUARD | 7/1/17 | 8/15/17 | 6.29.17: Michael Plant emailed Patty. See CIP ticket for comments. | Portal Guard | ycccd.edu | Colleague | ||||||||||
290 | Woodland Community College | 292 | Yes | PORTAL GUARD | 7/1/17 | 8/15/17 | 6.29.17: Yuba CCD ready to start proxy integration (Portal Guard) and Canvas, Apply. | Portal Guard | ycccd.edu | ||||||||||||
GAVILAN | 440 | Gavilan College | 441 | Shib v2 | 7/7/17 | 9/7/17 | 9/5/17-Unicon Shib upgrade in-process–still waiting on college to setup a database view | gavilan.edu | Banner | ||||||||||||
MARIN | 330 | College of Marin | 334 | Other IdP Looking Glass | 7/12/17 | 7/31/17 | TBD | NEED | NEED | NEED | NEED | n/a | n/a | 7/12/17: Matt will work with Burton Schane regarding new metadata - encourage them to integrate with Proxy. | 7/12/17: Marin contacted Patty about updating their Admin & Report Center URLs with new metadata from new IdP "Looking Glass". Matt working with them now.. | marin.edu | Banner | ||||
MENDOCINO-LAKE | 140 | Mendocino College | 141 | Engaged for Upgrade 7/25/17 | 8/21/17 | 10/21/17 | 9/18/17: College IdP metadata uploaded to Proxy Pilot/Prod (testing pending); Canvas metadata uploaded to Proxy Pilot (testing pending) | 9/14/17-Shib upgrade awaiting testing with Proxy | mendocino.edu | Colleague | |||||||||||
FEATHER RIVER | 120 | Feather River Community College | 121 | Unicon did Shib V3 | Unicon-Shib Upgrade Complete | frc.edu | Banner | ||||||||||||||
REDWOODS | 160 | College of the Redwoods | 161 | Shib V3 (? for sure?) | Unicon-Shib Upgrade Not Started: Redwood does not have infrastructure to support upgrade | redwoods.edu | Colleague | ||||||||||||||
PASADENA | 770 | Pasadena City College | 771 | Shib V2 (5/2/17: Working on DIY Upgrade) | 8/3/2017 Decided to upgrade Shib instead of using EIS. 8/8/17: Unicon Shib upgrade pre-requisite questionnaire sent (still awaiting response-sent follow-up email on 9/14) | pasadena.edu | Banner | ||||||||||||||
COPPER MOUNTAIN | 970 | Copper Mountain | 971 | Shib V2 | 9/18/17 | 11/18/17 | 9/18/17: Unicon Shib upgrade kick-off meeting conducted | cmccd.edu | Colleague | ||||||||||||
SAN JOSE-EVERGREEN | 470 | Evergreen Valley | 471 | Shib V3(Migrating to PortalGuard) | 7/27/2014: Changing to PortalGuard. Kickoff call 7-31 | Unicon-Shib Upgrade Complete | sjeccd.edu | Colleague | |||||||||||||
470 | San Jose City | 472 | Shib V3 | ||||||||||||||||||
YOSEMITE | 590 | Columbia College | 591 | ADFS | 9/22/2017 Tested attribute page. Waiting for Canvas configuration in Pilot. | Yosemite is using ADFS for their district IDP | yosemite.edu | Colleague | OEI 2 | ||||||||||||
590 | Modesto Junior College | 592 | ADFS | yosemite.edu | Colleague | ||||||||||||||||
PERALTA | 340 | Alameda | 341 | Shib V2 | 8/21/17 | 10/21/17 | 8/21/17-Unicon Shib Upgrade Kick-off Meeting conducted | peralta.edu | PeopleSoft | ||||||||||||
340 | Laney | 343 | Shib V2 | 8/21/17 | 10/21/17 | 8/21/17-Unicon Shib Upgrade Kick-off Meeting conducted | |||||||||||||||
340 | Berkley City | 345 | Shib V2 | 8/21/17 | 10/21/17 | 8/21/17-Unicon Shib Upgrade Kick-off Meeting conducted | |||||||||||||||
340 | Merritt | 344 | Shib V2 | 8/21/17 | 10/21/17 | 8/21/17-Unicon Shib Upgrade Kick-off Meeting conducted | |||||||||||||||
SAN DIEGO | 070 | San Diego City | 071 | - CIP-678Getting issue details... STATUS | Shib V2 | 8/21/17 | 10/21/17 | 9/13/17: Awaiting college to provide remote access | sdcccd.edu | Colleague | |||||||||||
070 | San Diego Mesa | 072 | - CIP-678Getting issue details... STATUS | Shib V2 | 8/21/17 | 10/21/17 | 9/13/17: Awaiting college to provide remote access | sdcccd.edu | Colleague | ||||||||||||
070 | San Diego Miramar | 073 | - CIP-678Getting issue details... STATUS | Shib V2 | 8/21/17 | 10/21/17 | 9/13/17: Awaiting college to provide remote access | sdcccd.edu | Colleague | ||||||||||||
070 | San Diego Adult | 076 | - CIP-678Getting issue details... STATUS | Shib V2b | 8/21/17 | 10/21/17 | 9/13/17: Awaiting college to provide remote access | ||||||||||||||
Inactive/Not Started
District | DIST MIS | College | MIS | JIRA | DIST IdP | IdP Solution | Start Date | TargetEnd Date | IdP Ready | Proxy Pilot | Proxy Prod | APPLY Pilot | APPLY Prod | CANVAS Pilot | CANVAS Prod | STARFISH Pilot & Prod | Proxy Status | IdP Solution Comment | IdP Domain | SIS | Initiative |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
VICTOR VALLEY | 990 | Victor Valley | 991 | vvc.edu | Colleague | OEI 2 | |||||||||||||||
SISKIYOUS | 180 | College of the Siskiyous | 181 | Shib V2 Ellucian | 3/20/17 | On Hold | 4/28/17-On hold: Siskiyous planning to use Ellucian's hosted services | Unicon - Shib Upgrade On-Hold | AEGIS | Banner | |||||||||||
SAN FRANCISCO | 360 | City of College of San Francisco | 361 | Yes | Portal Guard | College is switching to PortalGuard–Awaiting metadata | College upgrading to Portal Guard | ccsf.edu | Banner | EPI | |||||||||||
EL CAMINO | 720 | El Camino | 721 | Yes | Shib V3 | Ready for testing in Pilot- Pending review call with college | Unicon-Shib Upgrade Complete | elcamino.edu | Colleague | EPI | |||||||||||
GROSSMONT-CUYAMACA | 020 | Cuyamaca College | 021 | Shib V2 | gcccd.edu | Colleague R18 | |||||||||||||||
020 | Grossmont College | 022 | |||||||||||||||||||
LASSEN | 130 | Lassen Community College | 131 | ADFS | lassen.edu | Colleague | |||||||||||||||
NAPA VALLEY | 240 | Napa Valley College | 241 | napa.edu | |||||||||||||||||
SOLANO | 280 | Solano College | 281 | Shib V2 | solano.edu | Banner | |||||||||||||||
CHABOT-LAS POSITAS | 480 | Las Positas College | 481 | Shib v3 | clpccd.edu | Banner | |||||||||||||||
480 | Chabot College | 482 | Shib v3 | clpccd.edu | Banner | ||||||||||||||||
WEST VALLEY-MISSION | 490 | Mission College | 492 | Shib v3 | wvm.edu | Colleague | |||||||||||||||
490 | West Valley College | 493 | Shib v3 | wvm.edu | Colleague | ||||||||||||||||
WEST HILLS | 580 | West Hills College-Coalinga | 581 | whccd.edu | |||||||||||||||||
580 | West Hills College-Lemoore | 582 | whccd.edu | ||||||||||||||||||
ALLAN HANCOCK | 610 | Allan Hancock College | 611 | Shib V3 | Unicon-Shib Upgrade Complete | hancockcollege.edu | Banner | ||||||||||||||
El Camino CCD | 710 | Compton CCD | 711 | compton.edu | Colleague | ||||||||||||||||
NORTH ORANGE | 860 | Cypress College | 861 | Shib V2 CAS | nocccd.edu | Banner | |||||||||||||||
860 | Fullerton College | 862 | Shib V2 CAS | nocccd.edu | Banner | ||||||||||||||||
DESERT | 930 | College of the Desert | 931 | Shib V2 | desert.edu | Colleague | |||||||||||||||
RIVERSIDE | 960 | Riverside Community College | 961 | Shib V2 | rcc.edu | Colleague | |||||||||||||||
960 | Moreno Valley Community College | 962 | Shib V2 | rcc.edu | Colleague | ||||||||||||||||
960 | Norco Community College | 963 | Shib V2 | rcc.edu | Colleague |
Completed
District | DIST MIS | College | MIS | JIRA | DIST IdP | IdP Solution | Start Date | Target End Date | IdP Ready | Proxy Pilot | Proxy Prod | APPLY Pilot | APPLY Prod | CANVAS Pilot | CANVAS Prod | STARFISH Pilot & Prod | Proxy Status | IdP Solution Comment | IdP Domain | SIS | Initiative |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
WEST KERN | 690 | Taft College | 691 | Shib V3 | 7/10/17 | 9/10/17 | 8/8/17: Proxy Pilot/Prod, CCCApply Pilot/Prod and Canvas Pilot testing completed | Unicon-Shib Upgrade Complete | taft.edu | ||||||||||||
ANTELOPE VALLEY | 620 | Antelope Valley | 621 | Shib V3 | 8/2/17 Proxy integration complete | College-Upgrading; Pilot IdP environment updated but Prod IdP still outstanding | avc.edu | Banner | OEI 2 | ||||||||||||
MERCED | 530 | Merced College | 531 | Shib v3 | Proxy Prod update complete (also tested integrating with Canvas Pilot) | Unicon-Shib Upgrade Complete | mccd.edu | ||||||||||||||
BARSTOW | 910 | Barstow Community College | 911 | Shib v3 | 4/6/17 | 6/6/17 | 6/22/17- Proxy Prod and CCC Apply Prod testing successful 6/12/17-Proxy Pilot and Canvas Pilot testing successful 6/8/17-metadata uploaded to CCCApply pilot–testing successful | 5/31/17-Unicon-Barstow updated their certificate–Shib Upgrade Complete | barstow.edu | Banner | OEI 2 | ||||||||||
COAST | 830 | Coastline | 831 | Yes | Shib V3 | 5/8/17-Received reply from college to proceed with adding Canvas InCommon metadata 5/22/17 Eric tested Canvas pilot. Login worked, was concerned with the sign out and proxy cache. | Unicon-Shib Upgrade Complete | cccd.edu | Banner | OEI | |||||||||||
830 | Golden West | 832 | Shib V3 | cccd.edu | Banner | ||||||||||||||||
830 | Orange Coast | 833 | Shib V3 | cccd.edu | Banner | ||||||||||||||||
OHLONE | 430 | Ohlone | 431 | Shib V3 | 5/4/17 SLO issue with Canvas. Emailed Jason at Instructure to discuss. | Unicon-Shib Upgrade Complete | ohlone.edu | Colleague | OEI 2 | ||||||||||||
STATE CENTER | 570 | Fresno City | 571 | Yes | Shib V3 | Proxy Production update complete 6/6/17(Matt) Canvas beta configured wait 6/7/17 Testing beta and Canvas prod. | Unicon-Shib Upgrade Complete | scccd.edu | Colleague | EPI/MyPath CAI OEI | |||||||||||
570 | Clovis | 576 | Shib V3 | CAI | |||||||||||||||||
570 | Reedley | 572 | Shib v3 | 940 | |||||||||||||||||
SAN JOAQUIN DELTA | 550 | San Joaquin Delta | 551 | Shib v3 | Proxy Production update complete–testing complete | Unicon-Shib Upgrade Complete | deltacollege.edu | System 2020 | CAI | ||||||||||||
MT. SAN ANTONIO | 850 | Mt San Antonio College | 851 | DIY Shib V3 in-progress | Proxy Production update complete--testing complete | idp.mtsac.edu | Banner | OEI 2 | |||||||||||||
LAKE TAHOE | 220 | Lake Tahoe | 221 | Shib V3 | 5/8/17-Received reply from college to proceed with adding Canvas InCommon metadata. 5/11/17 Canvas Pilot tested successfully today. Asked Bill if he could give an ETA for prod. | Unicon-Shib Upgrade Complete | ltcc.edu | Colleague | OEI | ||||||||||||
MT. SAN JACINTO | 940 | Mt. San Jacinto | 941 | Shib V3 | 5/1/2017(Matt) Emailed Aaron Stafford to discuss prod IDP & Canvas. No response. | msjc.edu | Colleague | EPI OEI | |||||||||||||
FOOTHILL-DEANZA | 420 | Foothill | 421 | Yes | Shib V3 | 4/11/17-Added metadata for Starfish integration and conveyed to Michael R 5/1/17 Emailed Matt R. Foothill & DeAnza are ready to test with Canvas PILOT. Emailed Jason to add metadata. 5/8/17-Received reply from college to proceed with adding Canvas InCommon metadata 5/11/17(Matt) Metadata should be available. Matt R. will test Monday. 5/18/2017 Canvas Pilot configured for Foothill & DeAnza. Some concern about existing students w/o CCCID and the workflow. Matt R. will talk with staff if there is any issue during testing. | Unicon-Shib Upgrade Complete | fhda.edu | Banner | OEI | |||||||||||
420 | DeAnza | 422 | Yes | Shib V3 | |||||||||||||||||
VENTURA | 680 | Ventura | 681 | Shib V3 | 5/24/17(Matt) Configured Beta Canvas environment with proxy. Tested successfully, concerned that Staff/Faculty would require a CCCID if they are also listed as students in EduPersonAffiliation. | Unicon-Shib Upgrade Complete | vcccd.edu | Banner | OEI | ||||||||||||
680 | Oxnard | 682 | Shib V3 | ||||||||||||||||||
680 | Moorpark Colleges | 683 | Shib V3 | ||||||||||||||||||
MONTEREY | 460 | Monterey Peninsula College | 461 | Clearlogin | 4/13/17-CCC Apply metadata update complete-testing pending 5/4/17(Matt) Waiting for Canvas contact, need to followup. 5/30/17(Matt)Configured Canvas pilot. | College using Clearlogin | mpc.edu | OEI 2 | |||||||||||||
IMPERIAL | 030 | Imperial Valley | 031 | Yes | Shib V3 | 5/4/17(Matt) Emailed Jeff Cantwell about Canvas PILOT on 5/1, no reply. 5/31/17(Matt) Jeff forwarded my email to Omar Ramos and he was able to configure Canvas test/pilot. Omar will test and plan the production change. | Unicon-Shib Upgrade Complete | imperial.edu | Banner | OEI 2 | |||||||||||
SHASTA | 170 | Shasta | 171 | Yes | Portal Guard | 5/1/2017 Emailed James multiple times, no response. Awaiting metadata from college for Portal Guard IdP 6/6/17 Tested PortalGuard successfully. James forwarded Canvas documentation to the team that would do the configuration, will follow up on status. 6/14/17 James tested Canvas pilot, will roll out to Prod 6/15/17 | College upgrading to Portal Guard | shasta.edu | Colleague | OEI | |||||||||||
CERRITOS | 810 | Cerritos College | 811 | Shib V3 | 7/13/17-Cerritos completed remaining Canvas Pilot and Proxy Prod testing successfully | 5/31/17-Cerritos working to create a CCCID trait; once complete, pilot testing can begin | cerritos.edu | Peoplesoft | |||||||||||||
BUTTE-GLENN | 110 | Butte College | 111 | Yes | Portal Guard | 7/25/2017- Butte tested pilot & prod Canvas. | butte.edu | Colleague | OEI CAI | ||||||||||||
PALO VERDE | 950 | Palo Verde College | 951 | Shib V2 | 7/6/17 | 9/6/17 | 8/18/17-Apply tested successful and Canvas Pilot. | 7/06/17-Conducted Shib upgrade kick-off mtg | paloverde.edu | Colleague | |||||||||||
SAN BERNARDINO | 980 | Crafton Hills | 981 | Shib V3.3 | Need kick-off 7/26/17 | 7/31/17: Tested with Proxy Pilot successfully | DIY Shib upgrade - we need to get them configured for proxy and get their metadata uploaded for Apply. | sbccd.edu | Colleague | ||||||||||||
San Bernardino | 982 | Shib V3.3 | Need | See above | sbccd.edu | Colleague | |||||||||||||||
RIO HONDO | 880 | Rio Hondo College | 881 | Shib V3 (Unicon Upgrade 12/16) | Proxy Production update complete-testing complete | riohondo.edu | CAI OEI 2 |