The following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations. This project plan is not static and may change depending on how the circuit priorities change as impacted by construction, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule reflects the month that the college district was or will be contacted for a circuit upgrade evaluation meeting and review of the district’s network topology map. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.
July 2023
Contra Costa CCD
DVC San Ramon Center 1GB (secondary)
Los Rios CCD (3 centers moved to August)
Redwoods CCD
City of Hoopa 2x 1GB
August 2023
Citrus CCD
Citrus College 10GB (Rebid for Diversity)
Los Rios CCD
Cosmetology Center 1GB
Davis Center to West Sac Center 1 GB
El Dorado Center 1GB
Elk Grove Center 1GB
Mather Center 1GB
McClellan Center 2x 1GB
Twin Rivers Center 1GB
September 2023
Butte-Glenn Community College District
Chico Center 2x 1GB
Cosmetology Center 2x 1GB
Glenn County Center 2x 1GB
Skyway Center 2x 1GB
October 2023
Peralta CCD
Berkeley City College 2x 1GB
Solano County CCD
Vacaville Center 2x 1GB
Vallejo Center 2x 1GB
West Hills CCD
North District Office 1GB
November 2023
Shasta-Tehama-Trinity Joint CCD
Trinity Center 1GB (Rebid for Diversity)
December 2023
Coast CCD
Coastline Community College 10GB upgrade
Mendocino CCD
Covelo HS Center 1GB
January 2024
Desert CCD
Desert Hot Springs Campus 1GB primary
Indio Eastern Valley Center 1GB primary
Mecca/Therma Campus 1GB primary
Palm Springs Campus 1GB primary
Westfield Mall 1GB primary
February 2024
Desert CCD
Desert Hot Springs Campus 1GB secondary
Indio Eastern Valley Center 1GB secondary
Mecca/Therma Campus 1GB secondary
Palm Springs Campus 1GB secondary
Westfield Mall 1GB secondary
Hartnell CCD
Castroville Campus 1GB secondary
King City Center 1GB secondary
Soledad Campus 1GB secondary
Alisal Campus 2x 1GB - canceled duplicates
March 2024
Foothill-De Anza CCD
Foothill College 10GB (Rebid for Diversity)
Gavilan CCD
San Benito Campus 2x 1GB
San Diego CCD - district canceled all, using local fiber
San Diego City to Miramar College
Mesa College to Miramar College
San Diego Continuing Ed Centre City
San Diego Continuing Ed North City Campus
San Diego Continuing Ed Mid City Campus
April 2024
San Francisco CCD
Mission CC Center 1GB
May 2024
Siskiyous CCD
Yreka Campus 1GB (Rebid)
June 2024
Los Angeles CCD
East LA College 100GB upgrade (college-paid)
LA Valley College 100GB upgrade (college-paid)
Quarterly Progress on Circuit Installations
FY22/23 Circuits | Circuits Reprioritized and/or Added to Original Plan1 | Planned Prioritized Circuits2 | Circuits Implemented, In Production to Date | Planned Circuits Ordered, in Process of Implementation3 | Planned Circuits Pending Review and/or Order | Planned Circuits Canceled4 | Planned Circuits Rescheduled for Future Year5 |
---|---|---|---|---|---|---|---|
Quarter 1: July - September 2022 | 1 | 53 | 0 | 0 | 54 | 0 | 0 |
Quarter 2: October - December 2022 | |||||||
Quarter 3: January - March 2023 | |||||||
Quarter 4: April - June 2023 |
1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.
2 Includes all reprioritized and new circuit requests as noted above.
3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.
4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.
5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.
For Questions or More Information Contact:
CCC Technology Center:
Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org