The ColThe following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations. This project plan is not static and may change depending on how the circuit priorities change as impacted by construction, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule reflects the month that the college district was or will be contacted for a circuit upgrade evaluation meeting and review of the district’s network topology map. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.


July 2023

  • Contra Costa CCD

    • DVC San Ramon Center 1GB (secondary)secondary

  • Contra Costa CCD - New Request/Diversity

    • Contra Costa College 10GB diverse replacement

    • CCC Brentwood Center 1GB diverse replacement

    • Contra Costa CCD Office 2x 10GB upgrades

    • Diablo Valley College 10GB diverse replacement

    • Los Medanos College 10GB diverse replacement

  • Los Rios CCD (3 centers moved to August)

  • Redwoods CCD (originally met in and moved from 22/23; still trying to finalize plan)

    • City of Hoopa 2x 1GB

August 2023

  • CCCCO - New Request (initially met about installing RPI service)

    • CCC Chancellor’s Office 2x 10GB

    • CCCCO Data Center 10GB

  • Citrus CCD

    • Citrus College 10GB (Rebid for Diversity)

  • Los Angeles Valley - New Request/Diversity

    • LA Valley CC 2x 10GB (1 new, 1 diverse replacement)

  • Davis Center to West Sac Center

    Los Rios CCD

  • Cosmetology Center 1GB

  • (no response, 8 centers moved to September)

September 2023

  • Butte-Glenn Community College District (college’s network administrator on vacation, moved to October)

  • Los Rios CCD (evaluated, not ordered in 23/24)

    • Davis Center 1 GB

    • El Dorado Center 1GB

    • Elk Grove Center 1GB

    • Ethan Way Center 1GB - added

    • Mather Center 1GB

    • McClellan Center 2x 1GB

    • McClellan Diesel Auto Center 1GB - added

    • Natomas Center 1GB - added

    • Rancho Cordova Center 1GB

    • Twin Rivers Center 1GB

September
    • - canceled

    • West Sac Center 1GB

  • Solano County CCD

    • Vacaville Center 1GB

    • Vallejo Center 2x 1GB

  • West Hills CCD

    • North District Office 1GB

  • Yosemite CCD (originally met in 22/23, finalized topology and confirmed plan)

    • Columbia College (no physical circuits; e-lines to Modesto West & East Campuses)

October 2023

  • Butte-Glenn Community College District

    • Chico Center 2x 1GB

    • Cosmetology Center 2x 1GB

    • Glenn County Center 2x 1GB

    • Skyway Center 2x 1GB

October 2023

  • Peralta CCD (moved to Summer 2025, per district; building completion estimated 2026)

    • Berkeley City College 2x 1GB

  • Solano County CCD

  • Vacaville Center 2x 1GB

  • Vallejo Center 2x 1GB

    (moved to September 2023)

  • West Hills CCD

    • North District Office 1GB

November 2023
  • (moved to September 2023)

November 2023

  • San Luis Obispo CCD - New Request (can no longer access Cal Poly Slo fiber; needs fiber to SLO COE for diverse circuit)

    • Cuesta College 10GB secondary

  • Shasta-Tehama-Trinity Joint CCD

    • Trinity Center 1GB (Rebid for Diversity)

December 2023

  • Coast CCD (no response from college)

    • Coastline Community College 10GB upgrade

  • Mendocino CCD

    • Covelo HS Center 1GB

January 2024

  • Desert CCD

    Desert Hot Springs Campus 1GB primary

    (moved to January 2024 at district’s request)

January 2024

  • Copper Mountain CCD - New Request (diverse secondary; request to disconnect secondary circuit to College of the Desert)

    • Copper Mountain College 10GB

  • Desert CCD - New Request (moved 3 center sites to Feb 2024)

    • Indio Eastern Valley Center 1GB primary2x 10GB (NEW to move circuit from Copper Mountain College)

    • Mecca/Therma Thermal Campus 1GB primary

    • Palm Springs Campus 1GB primary

    • Westfield Mall 1GB primary

February 2024

  • Desert CCDMendocino CCD (moved from December 2023, at district’s request; unable to meet in January, moved to February)

  • Ventura CCD - New Request

    • Fire & Safety Training Academy 2x 1GB

February 2024

  • Sequoias CCD - New Request

    • Hanford Center 1GB

    • Tulare Center 1GB

  • Desert CCD (moved 1 center site to Jan 2024)

    • Desert Hot Springs Campus 2x 1GB secondary

    • Indio Eastern Valley Center 1GB secondary

    • Mecca/Therma Campus 1GB secondary

    • to CalREN

    • Palm Springs Campus 2x 1GB secondary

    • Westfield Mall 1GB secondary

    Hartnell CCD

    • Castroville Campus 1GB secondary

    • King City Center 1GB secondary

    • Soledad Campus 1GB secondary

    • 2x 1GB (1 shared with another center)

  • Hartnell CCD (moved to March, did not get scheduled in February)

    • Alisal Campus 2x 1GB - canceled duplicates duplicates canceled

  • Mendocino CCD (unable to meet in January, moved to February)

    • Covelo HS Center 1GB

March 2024

  • Foothill-De Anza CCD

    • Foothill College 10GB (Rebid for Diversity)

  • Gavilan CCD

    • San Benito Campus 2x 1GB

  • Hartnell CCD (moved to April, did not get scheduled in March as attendance at CISOA & CENIC Conferences limited availability)

  • San Diego CCD - district canceled all, using local regional dark fiber

    • San Diego City to Miramar College

    • Mesa College to Miramar College

    • San Diego Continuing Ed Centre City

    • San Diego Continuing Ed North City Campus

    • San Diego Continuing Ed Mid City Campus

April 2024

  • Copper Mountain CCD - New Request

    • 29 Palms Marine Base Center 1GB

    • Yucca Valley Center 1GB

  • Hartnell CCD (no response from district, April-June; moved to 2024-25)

  • Marin CCD - New Request

    • Marin-Bolinas Biology Lab Field Station 2x 1GB

  • San Bernardino - New Request

    • San Bernardino Economic Development & Corporate Training Center 2x 1GB

  • San Francisco CCD

    • Mission CC Center 1GB

  • San Francisco CCD - New Request

    • Chinatown Center 1GB

May 2024

  • Siskiyous CCD

    • Yreka Campus 1GB (Rebid)

June 2024

  • Los Angeles CCD

    • East LA College 100GB upgrade (college-paid)

    • LA Valley College 100GB upgrade (college-paid)


Quarterly Progress on Circuit Installations

FY22

FY23/

23

24 Circuits

Circuits Reprioritized and/or Added to Original Plan1

Planned Prioritized Circuits2

Circuits Implemented, In Production to Date

Planned Circuits Ordered, in Process of Implementation3

Planned Circuits Pending Review and/or Order

Planned Circuits Canceled4

Planned Circuits Rescheduled for Future Year5

Quarter 1: July - September

2022

2023

1

11

53

0

0

2

54

60

0

1

0

Quarter 2: October - December

2022

2023

11

57

0

4

56

8

2

Quarter 3: January - March

2023

2024

15

69

0

18

42

7

2

Quarter 4: April - June

2023

2024

15

69

0

43

19

7

2

Quarter 1: July-September 2024

Quarter 2: October-December 2024

1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.

2 Includes all reprioritized and new circuit requests as noted above.

3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.

4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.

5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.


For Questions or More Information Contact:

CCC Technology Center:

Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org

CENIC:

Ken Roberts, Project Manager CCC Segment kroberts@cenic.org

To Report Network Routing or Technical Issues:

CENIC NOC (available 24/7):

Email: noc@cenic.org

Phone: 714-220-3494