Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

The following college districts' circuits are currently scheduled for upgrade to 10GB or new 1GB circuits for center locations. This project plan is not static and may change depending on how the circuit priorities change as impacted by construction, circuit outage and diversity issues, new buildings and/or center locations, technology upgrades, etc. The schedule reflects the month that the college district was or will be contacted for a circuit upgrade evaluation meeting and review of the district’s network topology map. For more information on CENIC and the Broadband Infrastructure Upgrade project, check out the CENIC Public Documentation page.


July 2023

  • Contra Costa CCD

    • DVC San Ramon Center 1GB (secondary)

  • Los Rios CCD

    • Mather Center 1GB

    • McClellan Center 2x 1GB

    • Twin Rivers Center 1GB

    (3 centers moved to August)

  • Redwoods CCD

    • City of Hoopa 2x 1GB

August 2023

  • Citrus CCD

    • Citrus College 10GB (Rebid for Diversity)

  • Los Rios CCD

    • Cosmetology Center 1GB

    • Davis Center to West Sac Center 1 GB

    • El Dorado Center 1GB

    • Elk Grove Center 1GB

    • Mather Center 1GB

    • McClellan Center 2x 1GB

    • Twin Rivers Center 1GB

September 2023

  • Butte-Glenn Community College District

    • Chico Center 2x 1GB

    • Cosmetology Center 2x 1GB

    • Glenn County Center 2x 1GB

    • Skyway Center 2x 1GB

October 2023

  • Peralta CCD

    • Berkeley City College 2x 1GB

  • Solano County CCD

    • Vacaville Center 2x 1GB

    • Vallejo Center 2x 1GB

  • West Hills CCD

    • North District Office 1GB

November 2023

  • Shasta-Tehama-Trinity Joint CCD

    • Trinity Center 1GB (Rebid for Diversity)

December 2023

  • Coast CCD

    • Coastline Community College 10GB upgrade

  • Mendocino CCD

    • Covelo HS Center 1GB

January 2024

  • Desert CCD

    • Desert Hot Springs Campus 1GB primary

    • Indio Eastern Valley Center 1GB primary

    • Mecca/Therma Campus 1GB primary

    • Palm Springs Campus 1GB primary

    • Westfield Mall 1GB primary

February 2024

  • Desert CCD

    • Desert Hot Springs Campus 1GB secondary

    • Indio Eastern Valley Center 1GB secondary

    • Mecca/Therma Campus 1GB secondary

    • Palm Springs Campus 1GB secondary

    • Westfield Mall 1GB secondary

  • Hartnell CCD

    • Castroville Campus 1GB secondary

    • King City Center 1GB secondary

    • Soledad Campus 1GB secondary

    • Alisal Campus 2x 1GB - canceled duplicates

March 2024

  • Foothill-De Anza CCD

    • Foothill College 10GB (Rebid for Diversity)

  • Gavilan CCD

    • San Benito Campus 2x 1GB

  • San Diego CCD - district canceled all, using local fiber

    • San Diego City to Miramar College

    • Mesa College to Miramar College

    • San Diego Continuing Ed Centre City

    • San Diego Continuing Ed North City Campus

    • San Diego Continuing Ed Mid City Campus

April 2024

  • San Francisco CCD

    • Mission CC Center 1GB

May 2024

  • Siskiyous CCD

    • Yreka Campus 1GB (Rebid)

June 2024

  • Los Angeles CCD

    • East LA College 100GB upgrade (college-paid)

    • LA Valley College 100GB upgrade (college-paid)


Quarterly Progress on Circuit Installations

FY22/23 Circuits

Circuits Reprioritized and/or Added to Original Plan1

Planned Prioritized Circuits2

Circuits Implemented, In Production to Date

Planned Circuits Ordered, in Process of Implementation3

Planned Circuits Pending Review and/or Order

Planned Circuits Canceled4

Planned Circuits Rescheduled for Future Year5

Quarter 1: July - September 2022

1

53

0

0

54

0

0

Quarter 2: October - December 2022

Quarter 3: January - March 2023

Quarter 4: April - June 2023

1 Reprioritized circuits have been added to the original Planned Prioritized Circuits totals.

2 Includes all reprioritized and new circuit requests as noted above.

3 Implementations typically take 3-9 months or longer in some cases depending on project needs and are largely dependent on collaboration between the telecommunications carrier(s), CENIC’s PMs and engineers, sometimes local government (permits), and the college/district purchasing and installing or connecting equipment, then migrating and testing circuits. CCCTC and CENIC PMs regularly review circuits in this status and reach out to the carriers and colleges/districts as needed to keep things moving.

4 Circuit cancellations are based on college/district requests or due to “No Bid” from telecommunications carriers. Note that these are deducted from the “Planned Prioritized Circuit” totals above and are not cumulative for each quarter, only the number of circuits canceled within a specific quarter are counted.

5 Circuits rescheduled for the following fiscal year at the colleges' request AND deducted from the “Planned Prioritized Circuit” totals above.


For Questions or More Information Contact:

CCC Technology Center:

Cindy McCartney, Project Manager CCC Broadband Infrastructure Upgrade cmccartney@ccctechcenter.org

CENIC:

Ken Roberts, Project Manager CCC Segment kroberts@cenic.org

To Report Network Routing or Technical Issues:

CENIC NOC (available 24/7):

Email: noc@cenic.org

Phone: 714-220-3494