When a college is ready to integrate with the proxy the following internal and external steps must be completed:

Tip
Proxy On-boarding: Clone CIP-9 JIRA ticket template when creating a new College Proxy ticket. Make sure all sub-tasks are cloned with ticket.The following documents should accompany this checklist: Steps to Integrate with the SSO Proxy and CCC SSO Technical Implementation Guide
StepWho?DescriptionDocument / Link
1CollegeCollege has installed or upgraded Shibboleth v3 (or equivalent supported IdP)
 
Upgrade Shibboleth V2 to V3
2CollegeCollege
taken
takes steps to join InCommon Federation (Note:Not required at time of Proxy integration, but is highly recommended.)
 
Joining InCommon Federation
3CCCCCC
provides College with all required CCC SSO & IDP Proxy integration documentation and checklists* 
schedules kick-off meeting with college and ensures they understand all required Proxy integration documentation
4CCCCreates a CIP Proxy JIRA Ticket
(Clone CIP-9 with sub-tasks and revise title with college name & MIS code). PM updates the Master SSO Proxy Table with JIRA ticket link. 
and begins project management tasks 
5College

College

configures Pilot IdP per instructions provided** 

completes Steps A -F for Pilot & Production on Steps to Integrate with the CCC SSO Proxy 

Please contact Proxy Team if you have any questions
6CollegeCollege adds EntityID to metadata
 
See Steps to Integrate with the SSO Proxy
7CollegeCollege sends
InCommon metadata to PM or Unicon 
configured metadata to Proxy Project Team for upload to the Pilot proxy instanceProxy Team: Patty Donohue, CCC
Geneva Paliwodzinski, Unicon 
8CCCAttaches metadata to JIRA sub-task and assigns sub-task to Geneva P. 
9Unicon
Adds
Uploads metadata to Pilot environment for college testing. Notifies college to test. 
10CollegeCollege tests Proxy in Pilot and sends feedback to PM or Unicon
 
Send feedback to Proxy Project Team
11UniconUnicon moves metadata to Production for college testing
 12CollegeCollege configures Production IdP per instructions provided** 
Proxy Team will contact College when ready to test
13CollegeCollege confirms Production Proxy works
  
Send feedback to Proxy Project Team
14CCC
Works with college to integrate with Canvas 
If College has implemented Canvas: Complete steps to integrate Canvas with SSO Proxy See Integrate with Canvas
15CCC
Works with college to integrate with Hobsons
If College has implemented Hobsons: Contact SSO Proxy Project Team for proxy integration steps.Contact Proxy Project Team
16CCC
Works with college to integrate with EMSI
If College is implementing EMSI Career Coach - No additional steps are required. 
17CCCWorks with college to integrate with CCCApply V3 

*Documentation and checklists for SSO Initiative.